Road Closure – Harper Lane/Watling Street

Road closure and traffic management at Harper Lane/Watling Street junction, Radlett

As part of the installation of a signalised junction at Harper Lane/Watling Street in Radlett, the necessary closure of Harper Lane will be in effect from Monday 3rd August for a duration of 20 weeks.  The work is scheduled for completion on 17th December.

Phase A – 3rd August – 21st August

Road closure of Harper Lane and temporary off-peak two-way lights on Watling Street. Removal of white lines and splitter islands, carriageway safety improvements for re-directed traffic flows.

More information please click the link below:

https://www.harperlaneroadclosure.bloorhomes.com/?fbclid=IwAR0uC4tqrPfcWUzFpSumtfoVcY0HWd-Y2qBiUZsq_b_ce6UbvIXGSCE4tRM

Aldenham Parish Council are disappointed that there was no notice from HertsCC Highways and that the introduction of traffic lights again will cause problems in the village