Skip to content Skip to left sidebar Skip to footer

Phillimore Rec – Café Project

Please note in the week commencing 5th August 2024, the access road from Gills Hill to the depot/café may be narrowed, but still passable, as a new electricity power line needs to be installed.

In the week commencing 12th August, LifeBuild will be tarmacking the top of the trench, and the road will be very narrow.

In the week commencing 19th August, UKPN will be connecting the line installed by LifeBuild to the main network. This work will be on the junction of Gills Hill and the access track only.

APC apologises for any inconvenience these works may cause.